Economic Impact of Renewal

The Economics of Urban Renewal: A Cost-Benefit Analysis

How a formal cost-benefit analysis of a renewal scheme is built, shown with a labeled hypothetical you can check by hand, plus what such analyses tend to miss.

On this page
  1. What a cost-benefit analysis tries to do
  2. The usual steps
  3. A labeled hypothetical
  4. What cost-benefit analysis tends to miss
  5. How it relates to other tools
  6. Using a cost-benefit analysis wisely

What a cost-benefit analysis tries to do

A cost-benefit analysis (CBA) puts the costs and benefits of a project into the same units, usually money, so that they can be compared. For an urban renewal scheme, it asks whether the total benefits to society over time exceed the total costs. Public bodies use it to compare options, to justify spending and to decide whether a proposal deserves further study.

It is a framework for organizing judgments, not a machine that produces truth. Its results depend on the assumptions put in.

The usual steps

  1. Define the project and the alternative. Benefits and costs are measured against a baseline, often “do nothing” or a cheaper option. Choosing the baseline is itself a judgment.
  2. Set the scope. Decide who counts (residents of the area, the city, the region) and the time horizon.
  3. List costs and benefits. Include capital costs, ongoing operations and maintenance, and all benefits, direct and indirect.
  4. Put values on them. Some are easy, such as construction costs. Others, such as reduced noise or a safer street, need estimates.
  5. Discount to present value. Money later is worth less than money now, so future flows are converted to today’s terms.
  6. Compare. Compute net present value (benefits minus costs) and the benefit-cost ratio (benefits divided by costs).
  7. Test sensitivity. Change key assumptions and see how the result moves.

A labeled hypothetical

This example is invented for illustration. It describes no real project, and all numbers are hypothetical.

Suppose a city is considering rehabilitating a derelict block. The assumptions:

  • Up-front cost: $10 million.
  • Annual maintenance and operating cost: $0.2 million for 10 years.
  • Annual benefits: $2.0 million for 10 years (a bundle of items such as rents earned, taxes gained and costs avoided).
  • Discount rate: 5 percent per year.
  • Time horizon: 10 years, with no value after that, for simplicity.

To discount a steady annual amount for 10 years at 5 percent, multiply it by an annuity factor. That factor is (1 minus 1.05 to the power of minus 10) divided by 0.05, which is about 7.72.

  • Present value of benefits: 2.0 × 7.72 = about $15.44 million.
  • Present value of maintenance: 0.2 × 7.72 = about $1.54 million.
  • Present value of total costs: 10 + 1.54 = about $11.54 million.
  • Net present value: 15.44 − 11.54 = about $3.9 million. Rounded off, that is a little under $4 million.
  • Benefit-cost ratio: 15.44 ÷ 11.54 = about 1.34.

On these assumptions the project passes: benefits exceed costs.

Testing sensitivity

Now suppose benefits turn out 25 percent lower, at $1.5 million a year. The present value of benefits becomes 1.5 × 7.72 = about $11.58 million. Costs stay at about $11.54 million. The benefit-cost ratio is roughly 1.00 and the net present value is close to zero.

A one-quarter shortfall in benefits is enough to erase the case. That is the key lesson: a ratio of 1.34 looks comfortable, but it depends on estimates that are uncertain. Good analyses show a range, not one figure.

Changing the discount rate also matters. A higher rate shrinks the weight of later benefits and favors projects that pay off quickly. A longer horizon can do the opposite if benefits last.

What cost-benefit analysis tends to miss

Distribution. A CBA adds benefits across people. A project could pass while its costs fall on current tenants and its benefits on newcomers. Analysts sometimes report who gains and loses separately, and the distribution of benefits is a legitimate concern in its own right.

Hard-to-value effects. Community ties, cultural identity and the loss of familiar places are difficult to price. Environmental health effects and safety can be estimated, but the estimates are uncertain.

Double counting. Rising property values may already capture the value of better amenities. Counting both the amenity and the value gain counts the same thing twice.

Transfers versus real gains. A tax payment is a transfer from one party to another, not a net gain to society. Jobs moved from a neighboring area are not net new either.

Optimism and uncertainty. Cost overruns and slower-than-expected benefits are common in large projects. A single optimistic input can drive the result.

Option value and timing. Waiting, phasing or testing an idea on a smaller scale has value that a one-shot analysis may ignore. A feasibility study is one way to learn more before committing.

How it relates to other tools

A CBA looks at society as a whole. A developer’s development pro forma looks at private cash flows and returns. A project can pass the first but not the second, which is part of why subsidy debates occur: society may gain more than a private developer can capture, producing a financing gap.

Using a cost-benefit analysis wisely

Read the assumptions before the conclusion. Check the baseline, the discount rate, the horizon and who is counted. Look for sensitivity tests. Ask what the analysis leaves out and whether the omitted items would likely help or hurt the case.

Used honestly, CBA clarifies trade-offs and exposes weak spots. Used selectively, it can lend an air of precision to a conclusion that was settled in advance. The numbers help most when treated as an aid to judgment rather than a replacement for it.

The complete guide to economic impact of renewal

The Impact of Urban Renewal on Local Economies
Read the guide

Keep exploring